Carlile Office & Cross-Dock Facility, Anchorage – 1998

The team from the Carlile Truck Maintenance Shop, which we built in 1997, re-assembled for this new project. The team consisted of: Owner, Rock Partners; Architect, Cole & Thompson; Civil Engineers, DOWL; Tenant, Carlile Enterprises; Mechanical design-build subcontractor, Superior Plumbing & Heating; Electrical design-build subcontractor, Safe-T-Way Electric Inc./HZA Engineering. The project was a 30,000 square foot masonry and steel office and freight terminal complex on a 12-acre site in the Anchorage Industrial Park. While this project was not specifically design-build (the architect and civil engineer worked for the owner), we all worked together for four months to complete the design development. We obtained a building permit and broke ground in June, 1998. We completed the project in time to give it to Carlile for Christmas, 1998.